Altamont Pipeline – Livermore Reach

Livermore, CA

Owner:

Zone 7 Water Agency

Engineer:

Harris and Associates

Construction Manager:

Zone 7 Water Agency

Contract Value:

$23,817,930

Project Description:

This project consisted of the construction of a 42” diameter pipeline from the proposed Vasco Rate Control Station near Vasco Road to the Rate Control Station near Airway Drive in the City of Livermore, County of Alameda, and includes approximately 27,000 feet of 42” pipeline, three tunnel crossings, 2(42”) & 6(36”) Valves, miscellaneous appurtenances, and two rate control stations, and microtunnel under highway 580.

Project Information:

Status: Past
Category: Water Transmission,
Client Type: Municipalities, Zone 7 Water Agency,