Mission Bay Block 23A Site Utility Loop And Connections

Project Details

The Mission Bay Block 23A project involved the construction of the site utility loop extensions from the existing utility loop termination connections outside of UCSF’s Rock Hall Building to the new connections outside the new Block 23A Neurosciences Research Building to support the new building utility demand.

Scope of work was for the installation of civil utilities to within 5’ of the Block 23A building. Work included the demolition of existing landscaping and site work, excavation and trenching, installation of Manhole Vaults, Chilled Water, Steam, Sanitary Sewer, Storm Drain, Fire Water, Domestic Water, Electrical Duct Banks, Telecom Duct Banks and Generator relocation. Final phase of work was backfilling trench, installing new site work, asphalt paving and landscaping.

Project Info

Status: Current

Client Type:

OWNER

The Regents of the University of California

 

ENGINEER

Jacobs Engineering Group Inc.

 

CONSTRUCTION MANAGER

The Regents of the University of California

 

CONTRACT VALUE

$9,807,910