The Esplanade Storm Drain Repair project will re-route all storm drainage that flows through 380 Esplanade to a new outfall at 548-552 Esplanade. The work consists of installing concrete turning structures at Esplanade/Bill Drake Way and 548 Esplanade, 1300 linear feet of 60-inch HDPE pipe along Esplanade street right of way, and two 30-inch HDPE outfalls to be by auger bore or hand tunneled to daylight at the top of the existing revetment at 548 & 552 Esplanade. The project also includes the removal of two 18-inch outfall pipes at 400 Esplanade.
Status: Past
Category: Sewer Transmission,
Client Type: City,