Construction included a 12″ recycled water pipeline, recycled water services and fire hydrant laterals and appurtenances in Wood Hollow Dr., Redwood Blvd., and Olive Ave. from approximately STA 0+00 to STA 95+47. The work included excavation of approximately 490 CY of hard rock together with proper disposal of rock, trenching, sheeting, shoring and bracing, and installation of the 12″ recycled water pipeline inside an 18″ casing that was installed by HDD method. An additional 6500 LF of 12″ PVC was installed by HDD method.
Status: Past
Category: Water Transmission,
Client Type: Municipalities, North Marin Water District,