The work includes the construction of sanitary sewer facilities at multiple locations requiring a combination of pipebursting and open trench methods to upsize a 15” gravity sewer with 18” HDPE. Also, the replacement of manholes with new manholes and one drop sewer manhole; and rehabilitating existing manholes via recoating.
Replacing existing 6″ and 8” gravity sewer with new 8″ HDPE by pipebursting, constructing one new 6″ sewer collector, including one new manhole and two new cleanouts to collect sewage from six existing sewer laterals.
Constructing new 8″ PVC gravity sewer and reconnecting existing laterals as well as completing all associated street surface improvements.
Status: Current
Category: Sewer Transmission,
Client Type: City,