Fremont Union High School needed to replace their entire central infrastructure. This required some intricate timing hurdles to work while students were not on campus.
This project included the demolition and removal of the existing boilers that had severely aged and were leading to the failure of the pipeline infrastructure. After removal, Ranger installed replacement skid-type boilers in the central boiler room along with temporary capturing devices for any sediment that was circulating within the aging infrastructure. Pre-Construction services, project management, general conditions, boiler replacements
Project Info
Status: Past
Client Type:
OWNER
Fremont Union High School District
ENGINEER
C2G/Civil Consultants Group, Inc.
CONSTRUCTION MANAGER
Kitchell
CONTRACT VALUE
$1,285,991
CLIENT TYPE
Kitchell, Private/CG,