Ophir Road Pipelines

Project Details

The work involved a massive street-wide excavation and replacement for multiple pipelines at several locations. The pipeline construction consisted of 4,923 LF of 60″ treated water pipeline, 4,676 LF of 45″ raw water pipeline, 285 LF of 42″, 39″ and 36″ raw water pipeline, 9,799 LF of 18″ treated water pipeline, 6,217 lF of 12″ treated water pipeline, 88 LF of 6″ and 4″ treated water pipeline.

This included trenchless crossings of 1-80 and UPRR, three 60″ diameter steel casings, fiber optic conduit and manholes, outfall and crossing of Dutch Ravine, earthwork, twin 72″ corrugated metal pipes, concrete headwalls, 50 LF of 4 foot by 6 foot reinforced concrete box culvert, SCADA flow monitoring system, aluminum slide gate, tree removal, concrete and AC pavement replacement, US 40/Lincoln Highway CMU roadside monument, SWPPP implementation and monitoring, water system improvements and pump modifications at the Ophir Road Pump Station and corrosion control systems.

Project Info

Status: Past

Client Type:

OWNER

Placer County Water Agency

 

ENGINEER

Placer County Water Agency

 

CONSTRUCTION MANAGER

Placer County Water Agency

 

CONTRACT VALUE

$15,154,545